on the 6-8-1 screen, the budget that updates only includes the original budget and approve change order budgets. Unfortunately, most of the time, we are having to do work before we get an approved budget. I would like to have a box to check that would allow us to include open change order budgets (ideally, we could select which open ones to include) so we can see a true projected budget. We typically will not proceed with change order work unless we are certain the change order will later be approved.

We use this report to calculate our monthly projections and its always wrong and need to be massaged for the open change order budgets so the data isn't very accurate from operations to accounting.

Comments

  • Delivered in Version 26.2