It would be helpful if there was a warning indicating when a Sub Change order exceeds budgeted amount. Currently there is a warning if a subcontract exceeds budgeted amount; however, there is not a warning if a sub Change order is written causing the subcontract to exceed the budget. Recently an employee inadvertently added an extra zero to the change order. There was no warning and the change order went out.
by: Holly C. | over a year ago | Project Management