Votes
6
6-6-1 Overwriting a record# with same PO#
In v19.8 if I needed to change the vendor or other field from a saved PO, I was able to Copy and Paste the PO, make the necessary changes, and then type in manually the ...by: JJ S. | over a year ago | Last activity over a year ago | Status changed over a year ago | Project Management
-
Votes
6
Service WO column in daily field reports
Please add a WO # column in the daily field reports GRID so that people can attach some of their time directly to a service WO that is being assigned to that job. Right ...by: Charlene D. | over a year ago | Last activity over a year ago | Status changed over a year ago | Project Management
-
Votes
5
Change Order 6-4-1 Enhancement Request
It would be very beneficial to be able to enter "Assemblies" in the change order screen 6-4-1. Currently we have to use the takeoff to enter change orders that include ...by: Christy R. | over a year ago | Last activity 19 days ago | Status changed over a year ago | Project Management
-
Votes
5
Master PO - Multi Job
Allow Job field to be changed when creating the new sub-PO from a Master PO. We make agreements to purchase large quantities (example 200,000 pcs) from suppliers for ...by: Jerry A. | over a year ago | Last activity about a month ago | Status changed over a year ago | Project Management
-
Votes
5
Part numbers in Change Orders?
Why is there not a column for part numbers when creating a change order? There is a part number column in invoicing so why not in change orders?by: Lou F. | over a year ago | Last activity 2 months ago | Status changed over a year ago | Project Management
-
Votes
5
Net Change by Previous Change Orders
Why hasn't this been fixed. What a pain trying to get your Net Change by Previous Change Orders to populate correctly! Change Orders are often approved out of order so ...by: Lisa G. | over a year ago | Last activity over a year ago | Status changed over a year ago | Project Management
-
Votes
5
Invoice Multiple Customers under 1 Job Number
We have some jobs that we need to be able to invoice to multiple customers. Currently if we change the customer related to a job it changes all previous documents and we ...by: Dawn D. | over a year ago | Last activity over a year ago | Status changed over a year ago | Project Management
-
Votes
5
in 3-5 I would like to add another Job Status. We now have 1 to 6 I ...
In 3-5 the Job Status there is 1- Bid 2- Refuse 3-Contract 4-Current 5-Completed 6-Closed We use 3-Contract for Job that we have the contract but we ...by: Corrina W. | over a year ago | Last activity over a year ago | Status changed over a year ago | Project Management
-
Votes
5
Subcontract Report that shows Approved Change Orders with the Sub
Report 6-7-2 only has 2 options for subcontracts and it only shows the original bid. There should be a report that can be printed off that shows the base bid amount plus ...by: Jeff B. | over a year ago | Last activity over a year ago | Status changed over a year ago | Project Management
-
Votes
5
Change Order Details
When entering a change order request, the 'approved' amount automatically enters in as well. Can it stay blank until i actually go in and approve the change order, as it ...by: Sherri S. | over a year ago | Last activity over a year ago | Status changed over a year ago | Project Management
-
Votes
5
Create a report that shows cost vs billing for change orders.
Sage has no way to track cost for change orders and no work around. How can this be?by: Michael S. | over a year ago | Last activity over a year ago | Status changed over a year ago | Project Management
-
Votes
5
6-6-1 Yellow Notes visible at 12-4
Can you make the yellow notes in 6-6-1 viewable in 12-4? This allows a Purchaser to send a note to the Receiver when the materials arrive.by: Rick S. | over a year ago | Last activity over a year ago | Status changed over a year ago | Project Management
-
Votes
5
Purchase order report by budgeted cost code- for material and sub cost ...
We need to see what purchase orders were written for which cost code so we can decipher between po's. We also need to see this so we can see if our pm's are properly ...by: Shawn E. | over a year ago | Last activity over a year ago | Status changed over a year ago | Project Management
-
Votes
5
Make Sage100C Accessible by Phone/Tablet
Sage software has all the features that I need, however a modern business needs mobile capability. I need a way for technicians in the field to be able to use Sage on a ...by: Travis F. | over a year ago | Last activity over a year ago | Status changed over a year ago | Project Management
-
Votes
5
job status on job report
For System (not modifiable) reports, please add the Job Status as a criteria to all (committed cost reports would be an example). Without a limiting factor that is ...by: Tim L. | over a year ago | Last activity over a year ago | Status changed over a year ago | Project Management
-
Votes
5
Restrict the usage of cost codes that are not in the budget
If you create a Purchase Order or an Inventory Allocation and use a cost code that is not in the budget, a warning should pop up advising that "the cost code you are ...by: Jen L. | over a year ago | Last activity over a year ago | Status changed over a year ago | Project Management
-
Votes
5
Change Orders - Have Phases as a column option to enter in the Prime ...
In Change Orders, whether in the Prime or the Budget/Sub, can Sage add in the Phase Column? We do some projects with Phases, and when it comes to change orders, we would ...by: Jan K. | over a year ago | Last activity over a year ago | Status changed over a year ago | Project Management
-
Votes
5
F7 security labor job costs
Sue Collins would like to be able to prevent Payroll Labor costs from being drilled down to in job cost reports to protect the confidentiality of employee wages from ...by: tracy w. | over a year ago | Last activity over a year ago | Status changed over a year ago | Project Management
-
Votes
5
Add Subcontract Balance to 3-5 Subcontract Lookup
Adding a column for the Remaining Subcontract Balance would be a great addition to the 3-5 Jobs Subcontract screen. This would help give a quick reference audit for the ...by: Heather T. | over a year ago | Last activity over a year ago | Status changed over a year ago | Project Management
-
Votes
5
Budget $$ by cost code compared to PO $ by cost code
We should be easily able to see what we budgeted by job/cost code vs what has been committed on PO by job/cost code. To make sure our detail is in line with the total.by: Shawn E. | over a year ago | Last activity over a year ago | Status changed over a year ago | Project Management