In Pervasive we were able to have an "Assembly" layout layout column in the Takeoff Order view. It appears it is no longer there after upgrading to SQL.
We utilize the takeoff order tab as a way to take the project off in a way similar to how you would build the project. Now, without the assembly sort column, all my items blur together and there is no separation.
Is there a way to incorporate that into Takeoff order?
by: David S. | over a year ago | Other
Comments
Setting up a Sequence of Assembly_Phase does NOT reflect takeoff order, agreed there needs to be a way to show this. Sage please incorporate. an estimate is not merely a pricing tool, it is often the *communication* tool for understanding and discussing project scope from preconstruction through claims phases. A good estimate that reflects the how and the sequence of the how the job will be built is invaluable. Its not enough to have a jumble of items and prices.
As of 20.1 we've added the Assembly field so that it can be added to your layouts