So editing WBS values - takeoff unit is able to be imported, but not takeoff value. So if I am importing bids items for instance for unite price bids I get value, description, unit of measure but not the actual takeoff value? Missing 1/4 of the work that needs to be done for unit price bids.
by: Mike O. | over a year ago | Other
Comments
This is a barrier to civil/heavy contractors, including the largest, from using Timberline.
Thank you for your submission, we have added it to our backlog and will prioritize accordingly.
You can enter later on the over line takeoff values - I bring those in with the notes field and then manually type them in later on.