• Votes

    7

    Job Costs should be separated by actual part number and quantity, not ...

    It doesn't help me to see a lump of Cost Codes on a report. I would like the Job Costs to be separated by actual parts, with quantities visible, so I can make informed ...
  • Votes

    5

    Fix A/R Aged Call Sheets - reporting same information in both CURRENT ...

    We regularly use report # 3-1-5-56 and after update 19.5 in December 2014, the report is now showing the same invoice amounts due in both the Current and the 1-30 day ...
  • Votes

    4

    progress billing report jumbles all the line items

    when printing progress billing the report should not rearrange the order of the line items. the report should print in the order it is entered line by line
  • Votes

    3

    Canadian Edition: 3-7 Progress Billing report

    Allow the user to select the order in which line items from the 3-7 Progress Billing application print on the 3-7-21 report. Some users do not wish to print by Cost Code ...
  • Votes

    5

    Print Electronic Receipt Automatically Upon Processing

    The Electronic Receipt should appear automatically upon processing through Sage Payment Solutions. You can then have the option to print or not. As it currently stands, ...
  • Votes

    8

    Allow receivable overpayment without applying to retention

    Allow receivable overpayment without applying to retention
  • Votes

    9

    Please included a Pick List for individual invoices and/or record ...

    When billing T&M, often times we will bill only for specific invoices. Also, the record numbers and/or dates of the AP invoices may not be in sequence. Sometimes there ...
  • Votes

    3

    The ledgers do not agree to the trial balance

    The A/R sub-ledgers do not always agree to the trial balance. I have only had once experience where the sub-ledger actually agreed to the trial balance. I should be ...
  • Votes

    5

    When a job has been set up for progress billing, there need to be a ...

    It's very cumbersome to have to add codes after the fact when they should just be changed.
  • Votes

    9

    3-10 T&M being able to set multiple 6-3 job cost to non billable at ...

    When recreating T&M being able to set the billing status to multiple job cost (6-3) to billable or non billable all at once.
  • Votes

    7

    Transfer Client PO# to invoice when doing Progress Billing

    When doing Progress Billing, the invoice that is generated in 3-2 should automatically bring in the Client PO# from the corresponding job card (3-5)
  • Votes

    2

    WIP labour costs should be split out (wage, CPP, EI...)

    Currently if we have a WIP job, the labour costs go to the WIP account as one giant lump sum. It lumps the wage, CPP, EI, vacation etc all together. At the end of a ...
  • Votes

    9

    Change manage period availability to be able to seperately lock AR & ...

    We usually finish posting our AR far before we finish posting AP for any given month. It would be nice to be able to lock a period for AR separably from AP.
  • Votes

    7

    Add a line to progress billing

    I would like to adda line item in the middle of my Progress billing without retyping the whole thing?
  • Votes

    3

    Daily invoicing, including labour

    Please provide a way to create a computed daily timecard in order to daily invoice in T& M billing. Right now you can only create weekly, bi-weekly etc. timecards to T&M ...
  • Votes

    1

    Display all Client Addresses on One Tab

    In Sage 100 Contractor, the receivable clients have one tab for "Address 1" and a separate tab for Bill Address and Shipping Address. It would be handier to have them ...
  • Votes

    6

    Select certified payroll by phase

    In 3-5 Job you can check box to Require Cert PR. We also use Phase, to distinguish between work onsite or off. Employees may work both onsite and off, so excluding from ...
  • Votes

    7

    Progress billing-phases-change orders

    We periodically have 2 contracts issued for a project where labor and materials might be separated by the GC on tax exempt projects. We were instructed to utilize ...
  • Votes

    5

    invoices created from progress billing

    Should be able to click on invoices at 3-2 and go to source (3-7) without having access to the General ledger 1-3 screen. Besides the obvious security reasons ( ie: ...
  • Votes

    11

    A way to track collection calls on the Client.

    In Sage 300 there is a module to help track collection calls. I would like to see a way that we can put notes in so the client does not get multiple collection calls.