• Votes

    6

    Add Dates in Dispatch Board on Top Row

    Hello - For Sage 100 Contractor, it would be immensely helpful to have the dates populate on the top row of the dispatch board in the week view vs just the names of the ...
  • Votes

    2

    update 10-3 schedule from POs AND Subcontracts

    Make the task in POs and Subcontracts link to the 10-3 schedule and either automatically update or automatically pop up option to udpate tthe schedule. The Subcontracts ...
  • Votes

    3

    Administrators should be Administrators

    As an administrator I can only see my scheduled reports. How can I administer a system when I don't have access to everything? When others have trouble running reports ...
  • Votes

    1

    10-3 - Use the same task more than once in a schedule

    The program does not currently allow you to use the same task twice in a schedule. This would save a lot of time and duplicate tasks if we could.
  • Votes

    9

    Dispatch Board / Work Order Screen

    We need to have more options in the 11-2 under status example: when the work order is created it stays wok order, but once the tech completes the work there is nothing to ...
  • Votes

    1

    Adding Service Area tab as a column on Dispatch

    There are two areas on top of each work order that are color coded that show on each work order on the dispatch board. First is priority and the other is service area. ...
  • Votes

    5

    Scheduled Reports in Excel

    Save or send emails for scheduled reports in EXCEL files.
  • Votes

    1

    PDF Attachment Option when Emailing Techs Directly from the Dispatch ...

    Include the work orders as an attachment when emailing technicians directly from the dispatch board. This option is available when emailing from the work order itself, ...
  • Votes

    14

    a fix to the dispatch board.

    A workorder that is not completed but employee has gone out on job, I would like it to show up on the dispatch board as unassigned so that anyone can go out on it. I need ...
  • Votes

    10

    Show completion percentage on schedule

    I need to show my clients on a regular basis how complete each task is. We typically have a job site meeting every 2 weeks and at that meeting I present an adjusted ...
  • Votes

    6

    Import description from take off to schedule

    You should be able to import the descriptions used in the take off directly to the schedule. I know that the schedule is build off task lists, but you should be able to ...
  • Votes

    14

    Make the Dispatch Board in a month view

    It would be nice to see upcoming work further than 1 week. Also most of my customers are trying to schedule out a week to two weeks out, is a real pain on this system. I ...
  • Votes

    5

    Restore arrows to display the next record.

    Restore arrows to display the next record in 10-3 schedules. It was in there prior to the version 19 update.
  • Votes

    4

    Resource Management - dashboard for employees/equipment resource mgt ...

    We need help managing and scheduling our manpower and equipment resources. We should be able to assign resources to a dept and then have a calendar that we can schedule ...
  • Votes

    5

    Reminders for tasks within scheduling.

    To have reminders in scheduling that would remind you when different tasks are starting, their duration, and if they have a subcontractor vender. Something that would ...
  • Votes

    4

    Add Client Schedule based off Schedule to Sage 100 Contractor

    In the Schedule Reports, I would like to be able to generate a client schedule based off the Owner Decision Task Type.
  • Votes

    19

    Please make gant charts exportable to MS excel. Several clients use MS ...

    Gant chart does not export to MS excel. Please make it export so clients can use the schedule in MS excel
  • Votes

    7

    Add predecessors in the Gantt Chart report printing

    Add the red predecessor lines like in the Gantt Chart view to the report that prints out.
  • Votes

    4

    Please make a report for the scheduling module that rolls up to show ...

    If there was a report that you could run that could roll up to include more than one job, that would show conflicts, and maybe a gnat chart that would be like an ...
  • Votes

    3

    Make the gant chart editable in field for task start dates, ...

    Having to go back and forth to the grid to make small changes to the schedule is a waste of time. If I could use the gant chart itself as an input field, it would make ...