• Votes

    3

    Report to show detail of Total Cost

    Need a report that you can run to show total cost in summary and detail by part number. Currently you need to run an indented costed BOM report and then manually ...
  • Votes

    8

    closed/completed work ticket re-opening option

    sometimes a work ticket is closed inadvertently for a variety of reasons. It would be very helpful to be able to re-open a fully completed work ticket in production ...
  • Votes

    6

    Search by vendor and customer alius part number in inventory inquiry.

    Search by vendor and customer alius part number in inventory inquiry. ref: SAGE 100 ERP Ver: 5.008
  • Votes

    14

    production management ability to reverse a completion transaction

    Sometimes a completion is entered wrong due to a UOM issue. We need the ability to reverse a completion or conduct a negative completion.
  • Votes

    7

    Production Management Work Ticket Template - Increase Hours Decimal ...

    As a manufacture we need to have at least six decimal places in the hours field to accurately calculate the labor cost for each step. With only two decimal places the ...
  • Votes

    6

    Design Production Management Labor Entry like Timecard

    Timecard allows punch in/out to job numbers and a repunch. This feeds payroll and Job Cost. PM Labor Entry has a punch in/out function that does not allow entry of a ...
  • Votes

    5

    Item Audit Report To Record System induced changes

    Item Audit Report does not record changes to unit cost if that cost is updated by using "Cost Roll-Up Register" for example. When tracking down price/cost changes it ...
  • Votes

    2

    Bill of Material Change Control

    Expand the Bill of Material Change Control module to allow adding an item to BOMs selected via search filter criteria. An example would be adding a QR code label to ...
  • Votes

    4

    Bring Back Material Substitutions to Production Management

    Please bring back work order (now ticket) material substitutions that were in work order to production management. This is a significant feature gap between WO and PM. ...
  • Votes

    2

    limit users who can transfer out of a specific warehouse

    need to be able to limit users who can transfer out of the hold warehouse all users who have access to inventory management should be able to add to the warehouse but ...
  • Votes

    5

    Show warehouse specific inventory quanitites on the work ticket

    Having the ability to see inventory levels for the specified warehouse would eliminate back flushing inventory from the wrong warehouse.
  • Votes

    12

    Item Memo to show up during receipt of goods

    We have several items where something needs to be done before they can go into general inventory. Some items need to be verified by engineering, some items must be pre ...
  • Not Planned

    4

    MRP and Maximum Stock Level

    Modification to MRP to use Maximum Stock Reorder Method when making reorder/make recommendations as it does on the Inventory Reorder Report. Currently MRP only recommends ...
  • Votes

    4

    Production management - when closing a work ticket, the inquiry screen ...

    When a closing of work tickets are performed the following do not happen: 1) the closing register only shows the work ticket being closed with the parent item. The dollar ...
  • Votes

    4

    Production management - when closing a work ticket, the inquiry screen ...

    When a closing of work tickets are performed the following do not happen: 1) the closing register only shows the work ticket being closed with the parent item. The dollar ...
  • Votes

    1

    Allow Dynamic Material in Production Management by user role

    This is a great idea but it should be limited as a security event or user/role
  • Votes

    1

    remove extra step in production management for a purchase order ...

    In the old work order system when a receipt of goods was created for a work order, it would update the work order and the general ledger to work in process. In the new ...
  • Votes

    2

    WT Variance post at close of WT

    Accounting rules state to recognize any variance of production when the WT closes not when it completes. If your WT takes months to complete or transactions post in ...
  • Votes

    5

    Need more accurate Costed BOM Report

    Currently the Costed BOM Report will drill down to all levels to use the raw component costs to add everything up. However, we have BOM assemblies that are purchased, so ...
  • Votes

    1

    Creating templates in production entry

    When creating templates in production management the buttons that will take you to next step should only work on the steps and not the template number and step. This will ...