• Votes

    8

    disallow Duplicate change numbers

    Right now the system allows two changes with the exact same number within the same job and there is no way to prevent it. At least a warning might prevent some ...
  • Votes

    9

    Allocate A/P invoice lines and Inventory Allocation lines to ...

    Currently, all job costs are created from the "job costs window". Unfortunately, the descriptions on the A/P invoice lines and inventory allocation lines have to be ...
  • Votes

    3

    In 6-2 Budgets, be able to type directly into the Notes field

    Anyone manually entering budgets would want this. Right now, it pops-up the Notes Entry window, takes a second to update (slowing you down) and flash your screen, you ...
  • Votes

    10

    The ability to assign a different department to each phase of a job

    I think it would be helpful if we could assign departments to a particular phase of a job, instead of only allowing 1 department to be selected in the main job window. ...
  • Votes

    8

    Allow alpha numeric for phase number.

    We need to be able to enter an alpha numeric phase number. For example: 4E or 4W for 4th floor east wing or 4th floor west wing. Our project managers track our costs by ...
  • Votes

    1

    Customize Change Order Requests

    Different GC's like to have or not have certain things shown on change order requests. One GC does not want the bottom portion of the change order amounts shown on it, ...
  • Votes

    6

    Change Orders 6-4-1 Add Tax District to calculate Sales Tax

    Just like in the Takeoff 9-5 there should be a "Tax District" column to calculate for sales tax as needed.
  • Votes

    3

    Add a California DIR Registration Number field

    Add a California DIR Registration Number field to 4-4. California also has a DIR # for public works contractors. It's as mandatory as a license number.
  • Votes

    8

    Allow PO#'s to be linked to subcontracts

    It would be nice if you were able to create po#'s through the 7-1 Subcontract screen. Much like how you can create po's in the 11-2 Work Order screen to have a po linked ...
  • Votes

    3

    Inspections field on Daily Reports

    It's extremely important to be able to track all inspections. Just has there is a place for Incidents or Meetings on the Daily Report, there needs to be one for ...
  • Votes

    25

    Cost Code Record Line Limit too Low

    We would like the ability to add more than 5000 rows in 6-Project Management > 5-Cost Codes.
  • Votes

    3

    Include Daily PR in Cost and Hrs to Complete

    It appears as though Daily PR costs and hours are NOT included in the Cost and Hrs to Complete. Uncomputed PR IS included. Daily PR being included would give the user ...
  • Votes

    1

    Make it easier to send Purchase Orders created from Requests For ...

    Please make it easier to send POs created from RFP by either leaving the PO window open after saving a new record (so that the one just created can be quickly recalled), ...
  • Votes

    6

    Job Cost Status - Mass Update

    I would like to be able to change the status on multiple job cost records at one time (example, from 1-Open to 3-Billed). This would be similar to what we do in parts ...
  • Votes

    4

    We would like to limit the number of users in a po at the same time to ...

    We have this ability in the takeoff screen but not the PO screen. This tends to cause issues if more than one user is in a PO at the same time and making changes. One ...
  • Votes

    2

    I would like to see description included in the labour cost report

    This info can be pulled from payroll 5-2-2
  • Votes

    3

    Want Warning in Paperless When A Cost Code Is Over Budget

    Currently, the only warning option in Manage AP Flow is to warn when the job as a whole is overbudget. I'd like to have the option to get a warning (as a processor and ...
  • Votes

    1

    Assign a task to a cost code

    Add the ability to add a task to each cost code
  • Votes

    3

    Relocate the Jobs menu to the Project Management menu

    Jobs are not really accounts receivable. We bill for a job, but the customer is the receivable. When setting up security, it makes way more sense for the 3-5 menu to be ...
  • Votes

    1

    SSO-Purchase Orders Without Pricing

    We would like to be able to attach purchase orders to jobs in SSO without the cost information. Our installers need to see the PO's but we do not want them to see the ...