• Votes

    6

    Cost Code Master List

    We used to use Maxwell and while Sage is better in many ways, I think Maxwell did many things better for Job Cost. There was a "master" cost code list that was used to ...
  • Votes

    43

    Lien Waiver Templates in Word

    We have found that the lien waivers are cumbersome to modify and design in Sage 100. Our old system (Maxwell Management Suite) used Word templates to create lien ...
  • Votes

    2

    Create a way to view Journal Transactions choosing between including ...

    There should be an option to view transactions without the voided ones getting in the way
  • Votes

    7

    Change Order - Tracking Time

    Change orders should be able to be tracked and billed similar to a T&M invoice as well as submitting a proposal. Using the Phases, particular change orders can be ...
  • Votes

    1

    In 3-5, under the project dates and sales information tab, I would ...

    Even after changing the headings (which is allowed) this does not automatically show up on reports. Can this be changed?
  • Votes

    1

    Invalid sales tax on row.

    There is a limit placed on the amount entered into the "Cost" column that will not allow for proper computation of Sales Tax when the "Cost" column entry exceeds ...
  • Votes

    18

    side by side comparison of two or more takeoffs, budgets, or proposals

    Be able to view and edit more than one takeoff, budget or proposal at once without having to print them. Alt. be able to create and save versions of a takeoff without ...
  • Votes

    8

    changing report 6-1-2-47 to calculate under budget and completion % by ...

    add to this report so it calculates amount under budget and % complete by cost code, phase and bid item.
  • Votes

    3

    Make the gant chart editable in field for task start dates, ...

    Having to go back and forth to the grid to make small changes to the schedule is a waste of time. If I could use the gant chart itself as an input field, it would make ...
  • Votes

    1

    sub-accounts specific to each general ledger account

    Trying to delete sub-accounts prior to deleting a general ledger account - the sub account # which is automatically assigned to the general ledger account (credit card ...
  • Votes

    15

    Make canceling or voiding a range of checks possible

    Currently you have to enter the checks one at time to cancel them. If you have like 14 checks you printed on by mistake you have to take the time to type each one in and ...
  • Votes

    11

    BE ABLE TO ENTER A JOB # TO AN ALREADY SAVED P.O. WITHOUT HAVING TO ...

    CURRENTLY WHEN WE CREATE A PURCHASE ORDER WITHOUT A JOB #, THE SYSTEM WILL ALLOW YOU TO SAVE CHANGES BECAUSE THIS FIELD IS NOT REQUIRED. HOWEVER IF WE LATER CREATE A JOB ...
  • Votes

    2

    Run two versions of software at the same time, or, update all archive ...

    To save time updating 7 years worth of data (IRS Requirement) held in many archive companies it should be possible to keep an older version of the software to run the ...
  • Votes

    4

    Job profitabilaty by date/period range

    Take report 6-1-4-71 and allow me to identify the date/period range. Also create this report with more than one job on the page ex. Over/under report. Best to add a ...
  • Votes

    3

    For archiving, it would be nice to specify a date range for ...

    Overhead expenses stay in the vendor record forever. I don't see any way to archive those costs to consolidate what is seen on the "paid invoices" tab.
  • Votes

    5

    Subcontract reports seem to be incomplete where you want to see the ...

    The grid for the Subcontract detail in the vendor record shows almost everything a report should contain. But if you try to print the grid, the change order values are ...
  • Votes

    4

    3-5 AR Jobs - Purchase Orders tab

    Would be easier if the Purchase Orders tab would display PO's in a more usable order, such as by PO number or date. Today, it's sorted by vendor NUMBER, which isn't the ...
  • Votes

    13

    The ability to operate in Cash Basis accounting

    Our business doesn't always allow for information input for costing to give us the proper revenue on our financial statements - therefore cash basis accounting should be ...
  • Votes

    3

    CANADIAN T4's

    First off the system should have the ability to create a PIER report the same as Sage 50 has. Secondly - contrary to what I have been told by your customer support ...
  • Votes

    1

    Display all Client Addresses on One Tab

    In Sage 100 Contractor, the receivable clients have one tab for "Address 1" and a separate tab for Bill Address and Shipping Address. It would be handier to have them ...