• Votes

    2

    We have some clients that require us to invoice them using there ...

    Additionally, on the job cost side you could review the cost based upon cost codes or client billing codes.
  • Votes

    2

    Abilty to charge a cost to a change orders and print job cot ve ...

    Add a field that would allow a cost to be billed against the change order/cost code. This would add the capability to create a job cost vs billing report and view the ...
  • Votes

    13

    Add a field to vendor reports that allow you to filter by job.

    There is no way in Sage to create a Job list of subcontractors and vendors.
  • Votes

    4

    In 1-7 General Ledger Accounts, add a TOTAL row which totals each of ...

    In 1-7 General Ledger Accounts, add a TOTAL row which totals each of the 3 columns (current year, previous year, and budget).
  • Votes

    2

    Add Copy All Button to General Ledger Budget

    When entering monthly budget dollars for a given G/L account, add a "Copy All" button which distributes amount placed in first month to ALL months.
  • Votes

    2

    Apply custom discounts at time of bill payment

    The discount column in the 4.3.1 screen is pretty much useless. The user needs to have the ability to include a discount at the time of invoice payment -- any custom ...
  • Votes

    6

    Evenly auto-distribute annual G/L account budget over 12 months

    It would be nice if you could enter an annual budget amount for a given G/L account and have that amount automatically evenly distributed over the 12 months of the ...
  • Votes

    1

    Purchase order needs a price per column

    In Canada product is commonly price per Each/1, C/100, M/1000. We would like to have a column inserted in the Purchase Order for this feature. We have found there is a ...
  • Votes

    5

    Retainage Accounts

    You should be able to set a default account (current asset) to hold the accumulating retainage on a job when you set it up in the 3-5. When you produce an invoice for ...
  • Votes

    2

    Client PO is not saved when you paste PO# in existing invoice

    When you have an existing invoice, and paste the Client PO# in the field then click save. then go back to the record, it doesn't save it. if you manually enter or type ...
  • Votes

    1

    Print Subcontract orders oddity

    In report 6-4-3;21, when you select to print all the vendors without a selecting a particular vendor, it 'omits' a line item for a vendor. The only reasoning i found was ...
  • Votes

    5

    Accrued vacation time

    Accrued Vacation and Accrual Rate fields do not work. that the system is not accruing vacation time despite the fact that the accrual rates for the relevant employees ...
  • Votes

    2

    Vendor prices not populating in Purchase Orders

    We create work orders for future maintenance visits, we populate the Invoice detail with the filters and belts that we need to order for the visit. When the visit is ...
  • Votes

    2

    In 3-6 Receivable Clients, Service Work Orders: Instead of having a ...

    In 3-6 Receivable Clients, Service Work Orders: Instead of having a "blank Invoice Date" column, it would be extremely beneficial to have it titled "DUE DATE" and ...
  • Votes

    8

    11-3 Dispatch Board: Able to see the APPT TIME on the board

    It would be extremely beneficial to see the Appointment time in the dispatch board so we are more efficient in keeping the appointments scheduled properly. Other than ...
  • Votes

    7

    Vendor number default

    Make it so that if a vendor number is higher than the default entry, you can still change default entry to be a number lower than the highest number.
  • Votes

    15

    Create a warning when a 4-2 invoice is created for a subcontractor ...

    When an invoice is created and mistakenly NOT posted to a Subcontract, it cannot be applied to the subcontract at a later date, when the problem is recognized. This opens ...
  • Votes

    7

    Progress Bill Backup Detail report

    We are a Cost Plus Construction Company. We provide a Detailed Backup of all costs to the client. To do this, we have to create a Time and Material Invoice as well as ...
  • Votes

    1

    Progress Bill that allows for variance adjustment line to calculate ...

    We are a Cost Plus Construction company. We contract a job as a budget, with the Profit & Overhead based on the budget as a percentage. We use the Progress Invoice to ...
  • Votes

    1

    Invoice type and Cost codes

    One of clients would like the cost code used to setup an invoice to be referenced or pulled into the Daily Payroll Entry when the job is complete. Currently the WO is ...